Indian Railways Increases Budget Allocation for New Lines, Gauge Conversion, and Doubling by Nearly 6 Times

Ministry of Railways

azadi ka amrit mahotsav

Indian Railways Increases Budget Allocation for New Lines, Gauge Conversion, and Doubling by Nearly 6 Times

Indian Railways Commissions 31,180 km of New Lines, Doubling, and Gauge Conversion in 2014-24, Over Twice the speed of 2009-14

Posted On: 27 NOV 2024 7:29PM by PIB Delhi

The Railway projects are surveyed/sanctioned/executed Zonal Railway-wise and not State/district-wise/region wise as the Railway projects may span across state boundaries.

As on 01.04.2024, across Indian Railways including North eastern region, 488 Railway Infrastructure projects (187 New Line, 40 Gauge Conversion and 261 Doubling) of total length 44,488 Km, costing approx. 7.44 lakh crore are in planning/approval/ construction stage, out of which, 12,045 Km length has been commissioned and an expenditure of approx. 2.92 lakh crore has been incurred up to March, 2024.

The Average Annual Budget allocation for New Line, Gauge Conversion and Doubling Projects across Indian Railways is given below:

Period

Average Outlay

Increase w.r.t. average allocation of 2009-14

2009-14

11,527 crore/year

2024-25

68,634 crore

Nearly 6 times

The details of commissioning of New Line, Gauge Conversion and Doubling across Indian Railways are given below:-

Period

Total Length Commissioned

Average Length Commissioned

Increase w.r.t. average commissioning during 2009-14

2009-14

7,599 km

4.2 km/day

2014-24

31,180 km

8.54 km/day

More than 2 times

In 2023-24, 5,309 km sections have been commissioned across Indian Railways.

Zone-wise/year-wise details of all Railway Projects including cost, expenditure and outlay are made available in public domain on Indian Railways website.

During the last 10 years i.e. FY 2014-15 till FY 2023-24, across Indian Railways, 297 projects (New Line, Gauge Conversion and Doubling) of total length 23,352 km, costing approx. `2.65 lakh crore have been completed.

Railway infrastructural Projects in the Northeast Region are covered by Northeast Frontier Railway (NFR) Zone of Indian Railways.

As on 01.04.2024, 18 projects (13 New Lines and 5 Doubling), of a total length of 1,368 km, costing `74,972 crore, falling fully/partly in North Eastern Region, are in planning/approval/construction stage, out of which 313 km length has been commissioned and an expenditure of `40,549 crore has been incurred upto March 2024.

Average Budget allocation for Infrastructure projects and safety works, falling fully/ partly in North Eastern Region is as under:

Period

Average Outlay

Increase w.r.t. average allocation of 2009-14

2009-14

2,122 crore/year

2024-25

10,376 crore

About 5 times

Moreover, Commissioning of sections (New Lines, Gauge Conversion and Doubling) falling fully/partly in the North Eastern Region during 2009-14 and 2014-24 is as under:

Period

Total Length Commissioned

Average Length Commissioned

Increase w.r.t. average commissioning during 2009-14

2009-14

333 km

66.6 km/Year

2014-24

1,728 km

172.8 km/Year

About 2.6 times

During financial year 2023-24, total 110 km has been commissioned in North Eastern Region.

The completion of any Railway project(s) depends on various factors like quick land acquisition by State Government, forest clearance by officials of forest department, deposition of cost share by State Government in cost sharing projects, priority of projects, shifting of infringing  utilities,  statutory  clearances  from  various  authorities, geological and topographical conditions of area, law and order situation in the area of project(s) site, number of working months  in  a year for particular project site due to climatic conditions etc.

Final Location Survey for New Rail line from Agthori – Dekargaon (155 Km) passing through Darrang District of Assam has been sanctioned.

This information was given by the Union Minister of Railways, Information & Broadcasting and Electronics & Information Technology Shri Ashwini Vaishnaw in a written reply in Lok Sabha today.

*****

Dharmendra Tewari/Shatrunjay Kumar

(Release ID: 2078092) Visitor Counter : 251